Friday, July 15, 2011

Meeting Notes 7/15/11

Melissa, Peter, Mike Norton
  1. Melissa requested a cost update on the pantry cabinets as well as a hard install date.
  2. Do a master closet layout.
  3. Do minor touch ups and repairs on 2nd floor floors.
  4. Have Buonato fabricate surround at fireplace.  Should be full pieces of material not tile.  Have Villanueva remove existing tile and prep for new.
  5. Remove corner cabinet in dining room and patch floor. 
  6. Remove the crown in the Dining Room and replace with new to match kitchen crown only larger. 
  7. Make sure that the front entry closet doors work smoothly.
  8. Gym Floor - Epoxy coat the floor for vapor and install 6 mil poly sheeting taped at all seams for moisture protection.  Lay 1/2" rigid insulation. Install floating floor over.  Give some inexpensive options for floor color.
  9. Install folding shelf/table to right as you walk in laundry room door.
  10. Smooth out all basement ceilings and walls and up stairs with plaster.
  11. Replace round railings on stairs with new.  Install on new ORB (Oil Rubbed Bronze) brackets and stain to match other railings.
  12. Add non-slip coating to master bath floor