Client Questions 9/1/11

I started thinking about things that should happen before next Fri at
8 am when the runner goes up the stairs, through the second floor, the
master carpet gets laid down and the living room carpet is installed.
Due to the nature of the woven rug, the rug place suggested we not put
down the plastic on top of the rug because it could pull apart the
rug.

Paint stuff
- Bannister from first to second floor DONE 9/2
- Paint living room and hallway trim, master closet DONE 9/2

Finish Master Closet
   - does any paint or anything need to happen? DONE 9/2
   - let me know when this will start and I will move all the boxes out

Master Bath
       -Is any more trim going in master bath? DONE 9/2
       - I will try and find sconces this weekend for master bath (I am slightly concerned that I will not be able to return the ones that we currently have if all the boxes have been discarded) OK
       - What do I need to do regarding the master shower?  Ross mentioned whatever I bought does not fit so if I could know exactly what specifications I need to order for that would be great.  Ross ordered something.  It will be here Tuesday.  I hope you like it?
     - countertop? 9/8
     - mirrors 9/6
     - install med. cabinet 9/6
    - what else needs to happen in there? Accessories. 9/6

I think the only other things on the second floor are:
   - electrical stuff (master bedroom, replace Grayson's light) 9/6
   - switch out shower and tub fixtures in Grayson's bathroom 9/6