- Melissa requested a cost update on the pantry cabinets as well as a hard install date.
- Do a master closet layout.
- Do minor touch ups and repairs on 2nd floor floors.
- Have Buonato fabricate surround at fireplace. Should be full pieces of material not tile. Have Villanueva remove existing tile and prep for new.
- Remove corner cabinet in dining room and patch floor.
- Remove the crown in the Dining Room and replace with new to match kitchen crown only larger.
- Make sure that the front entry closet doors work smoothly.
- Gym Floor - Epoxy coat the floor for vapor and install 6 mil poly sheeting taped at all seams for moisture protection. Lay 1/2" rigid insulation. Install floating floor over. Give some inexpensive options for floor color.
- Install folding shelf/table to right as you walk in laundry room door.
- Smooth out all basement ceilings and walls and up stairs with plaster.
- Replace round railings on stairs with new. Install on new ORB (Oil Rubbed Bronze) brackets and stain to match other railings.
- Add non-slip coating to master bath floor
This blog is a way for us to keep track of everything that we talk about, suggest or do at your home over the life of our working relationship. It is updated, usually, on a daily basis during the project. Here we will record daily activity on the job, list recommendations on products and materials and add articles that pertain to your home.
CLICK AN IMAGE TO ENLARGE
Showing posts with label Flooring. Show all posts
Showing posts with label Flooring. Show all posts
Friday, July 15, 2011
Meeting Notes 7/15/11
Melissa, Peter, Mike Norton
Thursday, May 26, 2011
- We decided to leave the family room floor at the current height and make a slight 1" ramp over 24"+ at the end of the kitchen peninsula.
- Laundry ceiling is being patched in as well as possible. Still a lot of stuff hanging down. May need to box later after we see how it looks.
- Decided to demo master bath shower room ceiling and relocate vent to the wall. All lightsin this area to be sconces adding one more on the window side at the toilet.
- Powder room door will be a left hand 2'0" door. Light switch to be on the outside of the room
- Powder room sink will be corner mounted.
- We will add a vent to the Master Bath shower/toilet area.
- We will try to reuse the existing kitchen vent hood. It may need a new stainless chimney to the ceiling.
- We will either fabricate or purchase a medicine cabinet for the Master Bath to be located in the closet wall to the right of the vanity. Tis can be wide enough to fit between two wall studs and no mirror necessary.
- We will install a full length mirror on the closet wall behind the bath door.
- We agreed to alter the trey ceiling in the family room to allow for a 12" bookshelf.
- We will alter the Unico system as necessary to make it work appropriately and fix installation issues as we deem necessary.
- We will demo master closet ceiling and frame up as high s possible.
- It was determined that all of the moisture in the basement was caused by humidity. We will figure out a dehumidification system for the basement.
- Melissa will contact the alarm company asap to get everything checked out.
- We went over the speaker location with the electrician agreeing to locations in the family room, Dining room (down low in wainscot), Living room and deck.
- We discussed repair of the front entry. The issue is that the copper roof over the capital was never installed correctly and had a board nailed through it. I suggest replacing it with a new copper roof. We will also open up the panels on both sides, clean them out and reinstall with new trim. Caulk and paint. This will be a T&M project.
- Rot repair on the basement sills turned out to be much worse than originally thought completely eaten by termites in places. We will need to disconnect the Unico system to access this area. Total work needed is unknown.
Labels:
Alarm,
Cabinetry,
Dehumidifier,
Demolition,
Flooring,
Laundry,
Lighting,
Mirror,
Plumbing,
Rot,
Speakers,