CLICK AN IMAGE TO ENLARGE
Showing posts with label Accessories. Show all posts
Showing posts with label Accessories. Show all posts

Friday, September 2, 2011

Client Questions 9/1/11

I started thinking about things that should happen before next Fri at
8 am when the runner goes up the stairs, through the second floor, the
master carpet gets laid down and the living room carpet is installed.
Due to the nature of the woven rug, the rug place suggested we not put
down the plastic on top of the rug because it could pull apart the
rug.

Paint stuff
- Bannister from first to second floor DONE 9/2
- Paint living room and hallway trim, master closet DONE 9/2

Finish Master Closet
   - does any paint or anything need to happen? DONE 9/2
   - let me know when this will start and I will move all the boxes out

Master Bath
       -Is any more trim going in master bath? DONE 9/2
       - I will try and find sconces this weekend for master bath (I am slightly concerned that I will not be able to return the ones that we currently have if all the boxes have been discarded) OK
       - What do I need to do regarding the master shower?  Ross mentioned whatever I bought does not fit so if I could know exactly what specifications I need to order for that would be great.  Ross ordered something.  It will be here Tuesday.  I hope you like it?
     - countertop? 9/8
     - mirrors 9/6
     - install med. cabinet 9/6
    - what else needs to happen in there? Accessories. 9/6

I think the only other things on the second floor are:
   - electrical stuff (master bedroom, replace Grayson's light) 9/6
   - switch out shower and tub fixtures in Grayson's bathroom 9/6

Tuesday, July 12, 2011

Client Questions - 7/10/2011

The house is looking great.  Thank you!  I delivered the outdoor speakers to the living room today and more fixtures arrived as well. A few questions:

1.  I was wondering if you wanted to meet at some point this week to discuss closet stuff perhaps?  It can be next week as well.
Would you like to meet this Thursday 7/14?  I could do early afternoon.

2. When do you want the counter tops by?
I just need the material and/or slab location as soon as you have it chosen.

3.  Are there other things I should be picking out/picking up?
We need the accessories for the bathrooms.  TP Holders,  Things that have nothing to do with us would be rugs, furniture and window treatments. 

4.  In the workout room (which looks better already without the paneling) we are going to put a tv on the wall opposite the new wall you guys built (so on the same wall as the boiler room).  We don't need to install cable up high we can just run a wire up there).  Are you guys re-doing the soffits in that room? I can't remember what Ross had said.  The windows look great in there as well!
The soffits are being built to cover the existing plumbing and AC.  We will also leave an access for the clean out that is in the wall above the fireplace.

5.  When ever the dumpster gets emptied I will come over and clean out the third garage so Mike has an easier time getting through that disaster area!
We'll let you know.  If you want to throw stuff in there now, its fine.

6.  I saw that Mike pried off the grates in the front hall.  How labor intensive $$ is all of that?  It looks much better without those!
I will ask Mike.  I know he was wrestling with a couple of them.